Question: If the project is behind schedule, the earned value (EV) is Group of answer choices a. More than the planned value (PV) b. Less than
If the project is behind schedule, the earned value (EV) is
Group of answer choices
a. More than the planned value (PV)
b. Less than the planned value (PV)
c. More than the actual cost (AC)
d. Less than the actual cost (AC)