Question: The Schedule Performance Index ( SPI ) is calculated by . . . Question 4 options: dividing Earned Value ( EV ) by Actual Cost
The Schedule Performance Index SPI is calculated by
Question options:
dividing Earned Value EV by Actual Cost AC
dividing Planned Value PV by Actual Cost AC
dividing Planned Value PV by Earned Value EV
dividing Earned Value EV by Planned Value PV