Question: When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions: Group of answer choices On whichever

When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions: Group of answer choices On whichever critical path affords the smallest cost increase. On whichever non-critical path affords the smallest cost increase. That will shorten all of the critical paths. That will shorten all of the non-critical paths