Question: If there is two tasks A and B. Task A starts at day 4 and ends at day 10, task B with duration of 5

If there is two tasks A and B. Task A starts at

If there is two tasks A and B. Task A starts at day 4 and ends at day 10, task B with duration of 5 days depends on Task A with Start-to-Finish Relationship (SF+2), the * ... finish date of Task Bis 1 3 Calculate the probability that the project will finish within 23 days, given that the project is estimated to finish in 21 days and the STD value for the critical path is * 2.54 0.7764 O 0.7852 0.5753 0.4547 O