Question: If two activities have the same most likely duration ( 6 days ) , however the first activity has a wider range ( optimistic duration
If two activities have the same most likely duration days however the first activity has a wider range optimistic duration pessimistic duration as compared to the second activity which statement is NOT correct:
Group of answer choices
Any of the answers listed
First activity has higher likelihood to take more than days.
It is hard to tell. It all depends on the situation.
First activity has higher expected duration, variance, and standard deviation than the second one.
First activity has higher expected duration but lower variance and standard deviation than the second one.
None of the answers listed