Question: If you have planned four consumer testing phases in your project but want to see what happens if you only need two of them, what

If you have planned four consumer testing phases in your project but want to see what happens if you only need two of them, what should you do?
Change two consumer testing phases to be manually scheduled
Inactivate two consumer testing phases
Change the duration of two of the consumer testing phases to 1 day for all of their subtasks
Copy two consumer testing phases into another project and delete them from the original project