Question: If your project estimate is 1 , 0 5 0 , 0 0 0 , your cost of risk management is 3 0 , 0
If your project estimate is your cost of risk management is and your contingency reserves are what will your project budget be if also have to add management reserves? Round your answer to a whole number.If your project estimate is your cost of risk management is and your contingency reserves are what will your project budget be if also have to add management reserves? Round your answer to a whole number.