Question: igniight QUESTION THREE A certain project has got the following activities together with their precedence relationships and associated durations. Activity 8 70- # Sol Coun

igniight QUESTION THREE A certain project has got the following activities together with their precedence relationships and associated durations. Activity 8 70- # Sol Coun Propaded Duration by A 3 B A 7 30 D B 8 E 5 F 6 G D, E 11 H F 8 1 D, E, H 7 J 2 K GU 7 L J 4. M J 2. N K, L, M 3 Required: Draw the network diagram. 15 marts) Determine ES and LC for each activity and the critical activities and the project duration {6 mariss) Determine the free floats and the total floats for the critical activities and [4 marts) explain their meaning. GI 1) il)