Question: Immediate Activity Predecessors Normal Crash Time Time (Weeks) (Weeks) Normal Cost Crash Cost A 4 3 $2100 $2300 -- 2 1 $2200 $2500 B C

Immediate Activity Predecessors Normal Crash Time

Immediate Activity Predecessors Normal Crash Time Time (Weeks) (Weeks) Normal Cost Crash Cost A 4 3 $2100 $2300 -- 2 1 $2200 $2500 B C 3 3 3 $5000 $5000 D A 8 4 $2400 $2500 E 6 3 $1200 $1600 F 3 2 $3000 $3400 G D, E 4 2 $1500 $2800 A Start B End What is the incremental cost to crash activity G by 1 week (ie. how much more would it cost to shorten the time for activity G by 1 week)? Round your answer to a whole number