Question: Immediate activity Time (weeks) Predecessors Activity |Collect requirements |1 Analyze processes 2 Analyze data design processes 3 |6 5 design data 3 3,4 design screens

Immediate activity Time (weeks) Predecessors

Immediate activity Time (weeks) Predecessors Activity |Collect requirements |1 Analyze processes 2 Analyze data design processes 3 |6 5 design data 3 3,4 design screens design reports 4 4,5 6,7 program test and document |10 install 8,9 a) Draw a network diagram b) Calculate the earliest expected completion time c) Show the critical path in your network diagram d) What would happen if activity 6 were revised to take six weeks instead of two