Question: . Immediate Duration Activity Predecessor (Weeks) A 5 B - C B D A, C E A F D, E G D, F 224635 Table
Immediate Duration Activity Predecessor (Weeks) A 5 B - C B D A, C E A F D, E G D, F 224635 Table 1: Activities for the design of AON Network Diagram, assume FS dependencies between all activities. Identify each path through the project and its duration. What is the estimated project duration? Identify the critical path (CP) and its duration. Also, change the color of the arrows to RED to illustrate the CP visually. Identify all activities within the project that are a "Merge" activity. Identify all activities within the project that are a "Burst" activity. Identify one set of "Parallel" activities.