Question: Immediate Duration Activity Predecessor(s) (days) LS LF Slack A (5) H (2) ES EF 1 (3) A 5 C (5) B 2 C A, B

Immediate Duration Activity Predecessor(s) (days) LS LF Slack A (5) H (2) ES EF 1 (3) A 5 C (5) B 2 C A, B 5 E (5) D B 7 START C, D 5 F (3) E 3 FINISH G D 9 B (2) H E 2 D (7) I H 3 G (9) Completion time days Paths: Duration A-C-E-H-I