Question: Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? (c) Determine

Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? (c) Determine the critical path? (d) State the non-critical activities. (e) What is the implication of allowing activity B to spend extra 2 days instead of the slack number of days given in the table. B 1 5 14 D3 E G W 2 9 5 10 Activity t ES EF LS LF Slack A 5 Critical B 4 6 1 C 3 D 3 5 2 F 10 19 G 9 19 Y