Question: Immediate Optimistic Most Likely Activity Predecessors (Weeks) (Weeks) A B A IC A D B E DC F G H F E. G. HUH Consider

 Immediate Optimistic Most Likely Activity Predecessors (Weeks) (Weeks) A B A

Immediate Optimistic Most Likely Activity Predecessors (Weeks) (Weeks) A B A IC A D B E DC F G H F E. G. HUH Consider the tasks. durations, and predecessor relationships in the table above What is the probability of completion of the project before week 72 giveri that the critical path is A C F H 1-J? (rounded off to on 0 0.6 0 52 0 0.5 Moving to another question will save this response