Question: Immediate Predecessor Activity A B C D E F G B B B E A,D,C Time (days) Normal Crash 6 5 8 6 7 5

Immediate Predecessor Activity A B C D E F G B B

Immediate Predecessor Activity A B C D E F G B B B E A,D,C Time (days) Normal Crash 6 5 8 6 7 5 12 8 8 8 7 6 5 3 Costs ($) Normal Crash 20000 30000 15000 20000 10000 14000 11000 15000 9000 9000 5000 8000 3000 4000 Crash the project completely and find the optimal duration and associated minimum project cost