Question: Immediate Predecessor(s) Activity Optimistic Time Estimate( weeks) 2 2.5 none 3 4 B Pessimistic Time Estimates (weeks) 5 5 9 6 14 A Most Likely

Immediate Predecessor(s) Activity Optimistic Time
Immediate Predecessor(s) Activity Optimistic Time
Immediate Predecessor(s) Activity Optimistic Time
Immediate Predecessor(s) Activity Optimistic Time Estimate( weeks) 2 2.5 none 3 4 B Pessimistic Time Estimates (weeks) 5 5 9 6 14 A Most Likely Time Estimates (weeks) 3 4 7 5 6 5 5 5 3 A B,C B,C 4 D E F G H 2 8 4 7 6 9 : 1 4 7 11 G J 2 3 3 (a) Choose the right network diagram. B D F H J E G 1 B D F H J C E G O B D F H E G 1 B B D F H E G