Question: Using the information given, construct a network diagram using AON notation. Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks)

Using the information given, construct a network diagram using AON notation.

Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 3 6 9 none
B 3 5 7 A
C 4 7 12 A
E 5 10 16 C
F 3 4 5 D,E
G 3 6 8 D,E
H 5 6 10 F
I 5 8 11 G
J 3 3 3 H,I