Question: Using the information given, construct a network diagram using AON notation. Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks)
Using the information given, construct a network diagram using AON notation.
| Activity | Optimistic Time Estimate (weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) |
| A | 3 | 6 | 9 | none |
| B | 3 | 5 | 7 | A |
| C | 4 | 7 | 12 | A |
| E | 5 | 10 | 16 | C |
| F | 3 | 4 | 5 | D,E |
| G | 3 | 6 | 8 | D,E |
| H | 5 | 6 | 10 | F |
| I | 5 | 8 | 11 | G |
| J | 3 | 3 | 3 | H,I |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock