Question: Starting with original lab 4 data, which path(s) is/are the critical path(s) if activities B and D increase by 2 days, while activity H decreases

Starting with original lab 4 data, which path(s) is/are the critical path(s) if activities B and D increase by 2 days, while activity H decreases by 1 day?

Immediate Predecessor(s) A (5) H (2) Duration (days) 5n1(3) Activity ES EF LS LF Slack AnC (5) Bn2 CnA,B 5nE (5) DnSTART 7nB


Select one or more:

a. A-C-E-H-I

b. A-C-E-F

c. B-C-E-H-I

d. B-C-E-F

e. B-D-E-H-I

f. B-D-E-F

g. B-D-G

Activity A B C D E F G H I Immediate Duration Predecessor(s) (days) 5 2 5 7 5 3 9 2 3 A,B B C,D E D E H Completion time Paths: A-C-E-H-I ES Duration EF days LS LF Slack START A (5) B (2) C (5) D (7) E (5) G (9) H (2) F (3) 1 (3) FINISH

Step by Step Solution

3.50 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

CALCULATION ACTIVITY A B C D E f G H 1 FORMULA TIME CARLI START 5 2 5 7 5 3 9 3 ACEHI ACE F BCEH... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Human Resource Management Questions!