Question: Starting with original lab 4 data, which path(s) is/are the critical path(s) if activities B and D increase by 2 days, while activity H decreases
Starting with original lab 4 data, which path(s) is/are the critical path(s) if activities B and D increase by 2 days, while activity H decreases by 1 day?

Select one or more:
a. A-C-E-H-I
b. A-C-E-F
c. B-C-E-H-I
d. B-C-E-F
e. B-D-E-H-I
f. B-D-E-F
g. B-D-G
Activity A B C D E F G H I Immediate Duration Predecessor(s) (days) 5 2 5 7 5 3 9 2 3 A,B B C,D E D E H Completion time Paths: A-C-E-H-I ES Duration EF days LS LF Slack START A (5) B (2) C (5) D (7) E (5) G (9) H (2) F (3) 1 (3) FINISH
Step by Step Solution
3.50 Rating (170 Votes )
There are 3 Steps involved in it
CALCULATION ACTIVITY A B C D E f G H 1 FORMULA TIME CARLI START 5 2 5 7 5 3 9 3 ACEHI ACE F BCEH... View full answer
Get step-by-step solutions from verified subject matter experts
