Question: Which path(s) is/are the critical path(s) if activities B and D increase by 2 days while activity I decreases by 1 day? A-C-E-H-I A-C-E-F B-D-E-H-I

-
Which path(s) is/are the critical path(s) if activities B and D increase by 2 days while activity I decreases by 1 day?
- A-C-E-H-I
- A-C-E-F
- B-D-E-H-I
- B-D-G
A. Only iv
B. i and ii
C. i and iv
D. ii and iv
E. iii and iv
Please explain.
Immediate Predecessor(s) A (5) H (2) Duration (days) 5 1(3) Activity ES EF LS LF Slack A C (5) B 2 C A,B 5 E (5) D START 7 B F (3) E CD 5 F. E 3 FINISH G D 9 B (2) H E 2 D (7) | H 3 G (9) Completion time days Duration Paths: A-C-E-H-1Step by Step Solution