Question: Which path(s) is/are the critical path(s) if activities B and D increase by 2 days while activity I decreases by 1 day? A-C-E-H-I A-C-E-F B-D-E-H-I

Which path(s) is/are the critical path(s) if

  1. Which path(s) is/are the critical path(s) if activities B and D increase by 2 days while activity I decreases by 1 day?

    1. A-C-E-H-I
    2. A-C-E-F
    3. B-D-E-H-I
    4. B-D-G
    A.

    Only iv

    B.

    i and ii

    C.

    i and iv

    D.

    ii and iv

    E.

    iii and iv

Please explain.

Immediate Predecessor(s) A (5) H (2) Duration (days) 5 1(3) Activity ES EF LS LF Slack A C (5) B 2 C A,B 5 E (5) D START 7 B F (3) E CD 5 F. E 3 FINISH G D 9 B (2) H E 2 D (7) | H 3 G (9) Completion time days Duration Paths: A-C-E-H-1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!