Question: IMPORTANT NOTE Please do not use programs like matlab or excel. Please do all the calculations by hand. (3) The promoter of a rock concert

IMPORTANT NOTE
Please do not use programs like matlab or excel. Please do all the calculations by hand.
(3) The promoter of a rock concert in Indianapolis must perform the tasks shown in the table before the concert can be held (all durations are in days). (40 points) a) Draw the project network. b) Compute Early Event Times. c) Compute Late Event Times. d) Compute Total Floats. e) Determine the critical path. Activity Description Immediate Predecessors Duration A Find site 4 B Find engineers A 3 Hire opening act A 10 D Set radio and TV ads C 3 E Set up ticket agents A 5 F Prepare electronics B 4 G Check ads and agents D,E 7 H Set up transportation C 1.5 I Rehearsals F,H 2 J Last-minute details GI 3Step by Step Solution