Question: In 2 0 2 4 , Sheridan Corp. started a construction job with a total contract price of $ 1 7 5 0 0 0

In 2024, Sheridan Corp. started a construction job with a total contract price of $17500000. The job was completed on December 15,2025. Additional data are as follows:
\table[[,2024,2025],[Actual costs incurred during the year,$7050000,$8100000