Question: In a complex assembly operation, it is found the learning curve rate is 8 0 % . The standard time of 4 . 0 minutes

In a complex assembly operation, it is found the learning curve rate is 80%. The standard time of 4.0 minutes per assembly is reached after the 90th unit. Find the time required for the 100th unit.
17.03 minutes
3.87 minutes
5.57 minutes
 In a complex assembly operation, it is found the learning curve