Question: In a CPM Network, the critical path has six activities. Their durations are tabulated below. what is the expected duration of the project? DURATION Expected

 In a CPM Network, the critical path has six activities. Theirdurations are tabulated below. what is the expected duration of the project?

DURATION Expected Std. ACTIVITY Duration Deviation Variance Optimistic Most Likely Pessimistic (To)(Tm) (TP) (Te) (Ve) (se) B 2 3 5 D 4 8

In a CPM Network, the critical path has six activities. Their durations are tabulated below. what is the expected duration of the project? DURATION Expected Std. ACTIVITY Duration Deviation Variance Optimistic Most Likely Pessimistic (To) (Tm) (TP) (Te) (Ve) (se) B 2 3 5 D 4 8 13 F 5 6 8 K 3 3 3 N 7 10 15 S 3 5 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!