Question: In a CPM Network, the critical path has six activities. Their durations are tabulated below. what is the expected duration of the project? DURATION Expected




In a CPM Network, the critical path has six activities. Their durations are tabulated below. what is the expected duration of the project? DURATION Expected Std. ACTIVITY Duration Deviation Variance Optimistic Most Likely Pessimistic (To) (Tm) (TP) (Te) (Ve) (se) B 2 3 5 D 4 8 13 F 5 6 8 K 3 3 3 N 7 10 15 S 3 5 8
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
