Question: 5 . In a CPM network, the critical path has five activities. Their durations are tabulated next. Compute the following: a . The probability that

5. In a CPM network, the critical path has five activities. Their durations are tabulated
next.
Compute the following:
a. The probability that the project will finish by the end of day 32
b. The probability that the project will finish by the end of day 34
c. The probability that the project will finish before day 30
d. The probability that the project will finish on day 32
e. The probability that the project will finish no later than day35
A.
Activity Optimistic time Most likely time Pessimistic time Expected completion time of activity Std. Deviation Variance
A 2595.171.16666666666666671.3611111111111114
B 3484.50.83333333333333340.6944444444444445
C 4696.170.83333333333333340.6944444444444445
D 5102010.832.56.25
E 3595.3311
Sum 326.33333333333333410

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!