Question: In a one - shift operation, the operating time is 4 8 0 minutes and there are one 3 0 - minute lunch break and

In a one-shift operation, the operating time is 480 minutes and there are one 30-minute lunch break and two 15-minute rest breaks. What is the takt time if the demand rate is 70 units per day?
Multiple choice question.
8 minutes per cycle unit
5 minutes per cycle unit
6 minutes per cycle unit
7 minutes per cycle unit
10 minutes per cycle unit