Question: In a PERT network, non - critical activities that have little slack need to be monitored closely: because slack is undesirable and needs to be
In a PERT network, noncritical activities that have little slack need to be monitored closely:
because slack is undesirable and needs to be eliminated.
becruse they have a high risk of not being completed.
because nearcritical paths could become critical paths with small delays in these activities.
because they are causing the entire project to be delayed.
because PERT treats all activities as equally important.