In a project network, non-critical activities that have little slack need to be monitored closely because
A. slack is undesirable and needs to be eliminated
B. near-critical paths could become critical paths with small delays in these activities
C. PERT/CPM treats all activities as equally important
D. they are causing the entire project to be delayed
E. they have a kigh risk of not being completed