Question: In a PERT problem the expected completion time is known to be 115 days. Using the following times for activity A, the most likely time
In a PERT problem the expected completion time is known to be 115 days. Using the following times for activity A, the most likely time for activity A is:
| Activity | Optimistic | Most likely | Pessimistic |
| A | 180 | ??? | 300 |
A. 220
B. 210
C. 240
D. None of the above answers are correct
E. 230