Question: In a predictive project lifecycle: Question 1 3 Answer a . The deliverables are developed over multiple iterations where detailed scope is defined and approved
In a predictive project lifecycle:
Question Answer
a
The deliverables are developed over multiple iterations where detailed scope is defined and approved for each iteration when it begins.
b
The project deliverables are defined at the beginning of the project and any changes to the scope are progressively managed.