Question: In a project, activity A,B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A,B, and C are week 5

 In a project, activity A,B, and C are the predecessors (or

In a project, activity A,B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A,B, and C are week 5 , week 7 , and week 4 , what are the EST and EFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.)