Question: in a project network diagram, if Activity E has an early start ( ES ) of 7 days, a late start ( LS ) of

in a project network diagram, if Activity E has an early start (ES) of 7 days, a late start (LS) of 9 days, and a
duration of 3 days, what is the total float for Activity E?
5 days
0 days
2 days
3 days