Question: Construct the project network diagram using AON method Compute the early start, early finish and late start, and late finish for each activity. Compute the

Construct the project network diagram using AON

Construct the project network diagram using AON method

Compute the early start, early finish and late start, and late finish for each activity.

Compute the slack for each activity.

Find the critical path and the project duration

The following information has been gathered for a project: Activity Immediate predecessor activity Duration (days) D G 1. Construct the project network diagram using AON me 2. Compute the early start, early finish and late start, late activity. (4 marks) 3. Compute the slack for each activity. (4 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!