Question: In a resource - constrained project, the first, or primary, priority in assigning resources is usually given to activities with the Multiple Choice least slack.
In a resourceconstrained project, the first, or primary, priority in assigning resources is usually given to activities with the
Multiple Choice
least slack.
smallest duration.
lowest identification number.
highest cost.
most slack.