Question: QUESTION 36 In a resource-constrained project scheduling using heuristics, the first and second priority in assigning resources is usually given to activities with the O

QUESTION 36 In a resource-constrained project scheduling using heuristics, the first and second priority in assigning resources is usually given to activities with the O Least slack and minimum duration. O Least slack and lowest identification number. O Smallest duration and least slack. O Highest cost and highest float. O Most slack and minimum duration