Question: In a resource - constrained project, the third priority in assigning resources is usually given to activities with the In a resource - constrained project,
In a resourceconstrained project, the third priority in assigning resources is usually given to activities with the
In a resourceconstrained project, the third priority in assigning resources is usually given to activities with the
least slack.
smallest duration.
lowest identification number.
most slack.
highest cost.