Question: In a small engineering project, following activities, shown in the table, are involved. Activity Depends On Duration Labors/day A None 2 2 B None U

 In a small engineering project, following activities, shown in the table,

In a small engineering project, following activities, shown in the table, are involved. Activity Depends On Duration Labors/day A None 2 2 B None U C None D B E A, D F C G E. F AQUINN - What is the minimum contract duration (in days) if there are only 7 daily resources available and if it is assumed that having started an activity it must be completed without a break