Question: In an assembly operation with 3 components whose individual service level to the assembly line is 90%, the overall service assuming no issues in assembly
- In an assembly operation with 3 components whose individual service level to the assembly line is 90%, the overall service assuming no issues in assembly itself will be:
- 90%
- 81%
- 72%
- The scientific way to reduce cycle time without sacrificing TH is to:
- Reduce WIP but not below Critical WIP.
- Implement a six sigma program
- Implement a lean program
- Reduce WIP below Critical WIP.
- Assume you are on the marginal case curveif the desired throughput for the operation is a minimum of 450 units and customers need the product in no longer than 3 days, you could deliver these results by:
- Reduce WIP to 100 units
- Reducing WIP to 1500 units
- Increasing WIP to 2800 units
- None of the above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock