Question: In an MRP problem, A is an MPS item. Every A requires 2 B ' s and 3 C ' s . Every B requires

In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. Initial inventopry value for A is 100, B is 200, and C is 0. Use lot-4-lot method for order quantitiies for all items. If gross requirement for A is 800 in period 9, what will th eplanned-order release for B in period 5?