Question: In a MRP problem, A is a MPS item. Every A requires 2 B ' s and 3 C ' Every B requires 5 C

In a MRP problem, A is a MPS item. Every A requires 2 B's and 3C' Every B requires 5 C's. All lead times are two periods. All initial inventory values are 0. Use lot-for-lot method for order quantities for all items. What is the low level code (LLC) for B and C?
LLC for B is 0 and C is 1
LLC for both B and C are 2
LLC for B is 2 and C is 1.
LLC for B is 1 and C is 2