Question: In applying CPM , we note that the critical path is a path on which Group of answer choices each and every one of the
In applying CPM we note that the critical path is a path on which
Group of answer choices
each and every one of the activities has zero slack.
none of the activities have zero slack.
at least one activity has zero slack.