Question: In applying CPM, we note that the critical path is a path on which Group of answer choices at least one activity has zero slack.

In applying CPM, we note that the critical path is a path on which Group of answer choices at least one activity has zero slack. none of the activities have zero slack. each and every one of the activities has zero slack