Question: In assignment 1 , you considered the following project with 8 activities, labelled A to H : table [ [ Activity , Time (

In assignment 1, you considered the following project with 8 activities, labelled A to H :
\table[[Activity,Time (days),Precedence],[A,5,-],[B,11,A],[C,15,A],[D,9,A],[E,27,B,C],[F,17,C,D],[G,23,F],[H,13,G,E]]
Clearly define variables and propose a linear programming model to find the project's earliest completion time.