Question: In forward pass computation in a network diagram, if the next succeeding activity in the forward direction is a merged activity, which Early Finish figure
In forward pass computation in a network diagram, if the next
succeeding activity in the forward direction is a merged activity,
which Early Finish figure becomes the Early Start?
Select one:
A. The smallest Early Finish of all preceding activities
B. The largest Early Finish of all preceding activities
C. The mean Early Finish of all preceding activities
D. The average Early Finish of all preceding activities
E. The medium Early Finish of all preceding activities
All the following are part of the Three-Point Estimating
Method, EXCEPT:
Select one:
A. Most Likely Estimate
B. Optimistic Estimate
C. Pessimistic Estimate
D. Automated Estimate
E. (A), (B) and (C) are correct
Mike's boss has told him that his project is very important.
Because they have limited funding, the project has to be
delivered on a fixed contract sum. His project is therefore
constrained.
Select one:
A. Time
B. Cost
C. Quality
D. Performance
E. Resource
Portfolio of projects can be classified by type. Which of the
following describes projects that are must do projects:
Select one:
A. Compliance
B. Strategic
C. Operational
D. Promotional
E. Strategic and Compliance