Question: In forward pass computation in a network diagram, if the next succeeding activity in the forward direction is a merged activity, which Early Finish figure

In forward pass computation in a network diagram, if the next

succeeding activity in the forward direction is a merged activity,

which Early Finish figure becomes the Early Start?

Select one:

A. The smallest Early Finish of all preceding activities

B. The largest Early Finish of all preceding activities

C. The mean Early Finish of all preceding activities

D. The average Early Finish of all preceding activities

E. The medium Early Finish of all preceding activities

All the following are part of the Three-Point Estimating

Method, EXCEPT:

Select one:

A. Most Likely Estimate

B. Optimistic Estimate

C. Pessimistic Estimate

D. Automated Estimate

E. (A), (B) and (C) are correct

Mike's boss has told him that his project is very important.

Because they have limited funding, the project has to be

delivered on a fixed contract sum. His project is therefore

constrained.

Select one:

A. Time

B. Cost

C. Quality

D. Performance

E. Resource

Portfolio of projects can be classified by type. Which of the

following describes projects that are must do projects:

Select one:

A. Compliance

B. Strategic

C. Operational

D. Promotional

E. Strategic and Compliance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!