Question: In Drum-Buffer-Rope scheduling, what does each term represent? v Timed inventory kept before the bottleneck to protect it from interruptions. 1. Drum The constraint that

In Drum-Buffer-Rope scheduling, what does each
In Drum-Buffer-Rope scheduling, what does each term represent? v Timed inventory kept before the bottleneck to protect it from interruptions. 1. Drum The constraint that sets the speed of the system. 2. Buffer 3. Rope The signal generated by the constraint triggering release of new raw materials into the system