Question: In earned value analysis ( EVA ) , we found: B C W P = $ 3 2 , 6 0 0 , B C
In earned value analysis EVA we found: $$ and ACWP $ The project is:
a Behind schedule and overbudget
b Behind schedule and underbudget
c Ahead of schedule and overbudget
d Ahead of schedule and underbudget