Question: In earned value analysis ( EVA ) , we found: B C W P = $ 3 2 , 6 0 0 , B C

In earned value analysis (EVA), we found: BCWP=$32,600,BCWS=$29,650, and ACWP $33,900. The project is:
a. Behind schedule and overbudget
b. Behind schedule and underbudget
c. Ahead of schedule and overbudget
d. Ahead of schedule and underbudget
 In earned value analysis (EVA), we found: BCWP=$32,600,BCWS=$29,650, and ACWP $33,900.