Question: In evaluating time - cost trade - offs, we start by crashing the task on the critical path that: Multiple Choice Has the lowest crash

In evaluating time-cost trade-offs, we start by crashing the task on the critical path that:
Multiple Choice
Has the lowest crash cost to reduce by one unit of time.
Can be reduced the most.
Is the longest.
None of these.