Question: In evaluating time-cost trade-offs, we start by crashing the task on the critical path that: Multiple Choice Has the lowest total crash cost. Has the

In evaluating time-cost trade-offs, we start by crashing the task on the critical path that: Multiple Choice Has the lowest total crash cost. Has the lowest cost to reduce by one unit of time. O Is the longest None of these Can be reduced the most aw o search DI C