Question: In job order contracting, the contractor issues multiple call orders to the owner indicating the work that will be conducted on a project during a
In job order contracting, the contractor issues multiple call orders to the owner indicating the work that will be conducted on a project during a specified period of time.
Group of answer choices
True
False
For which type of contract does the owner provide book of unit costs to use for calculating how much will be paid for the work?
Group of answer choices
Unit price
Cost-plus
Cost-plus with GMP
Job order contract