Question: In making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start
In making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T?
Group of answer choices
the LS of the following activity plus the activity time of T
the LF of the following activity minus the activity time of T
the largest EF for the three activities that are immediate predecessors for activity T
the LS of the following activity minus the activity time of T
the smallest EF for the three activities that are immediate predecessors for activity T
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
