Question: Question 4 - answer is NOT C or D Question 4 In making a forward pass through a network, three activities are immediate predecessors for
Question 4 - answer is NOT C or D
Question 4 In making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? the LS of the following activity plus the activity time of T the LF of the following activity minus the activity time of T the largest EF for the three activities that are immediate predecessors for activity T the smallest EF for the three activities that are immediate predecessors for activity T the LS of the following activity minus the activity time of T 4 pts